|
Fletcher Construction was the contracted builder for the project while engineering firm Beca Group provided the design management and coordination, structural, geotechnical, civil, mechanical, electrical, plumbing, lighting and fire engineering services.
Harrison Grierson provided surveying services. It was designed by Craig Craig Moller architects and has received a New Zealand Institute of Architects National Award as well as regional awards.
Taking two year and 9 months construction time, the tower was opened on 17 August 1997, six months ahead of schedule.
Project Architect: Les Dykstra
Facts and figures
The tower is constructed of reinforced, high-performance concrete. Its 12-metre (39 ft) diameter shaft (containing three lifts and an emergency stairwell) is supported on eight 'legs' based on 16 foundation piles drilled over 12 m (39 ft) deep into the local sandstone. The main shaft was built using climbing formwork.
The upper levels were constructed from composite materials, structural steel, precast concrete and reinforced concrete, and the observation decks clad in aluminium with blue/green reflective glass. A structural steel framework supports the upper mast structure. During construction 15,000 cubic metres (20,000 cu yd) of concrete, 2,000 tonnes (2,200 short tons) of reinforcing steel and 660 tonnes (730 short tons) of structural steel were used. The mast weighs over 170 tonnes (190 short tons). It had to be lifted into place using a crane attached to the structure, as it would have been too heavy for a helicopter to lift. To then remove the crane, another crane had to be constructed attached to the upper part of the Sky Tower structure, which dismantled the big crane, and was in turn dismantled into pieces small enough to fit into the elevator.

So what must it be like to take the Sky Jump? Experience it here.
|